Requirements for Installation of Process Towers

Author:admin Time:2018-11-12 10:43:00
The installation of process towers must meet the following requirements:
(1) The design documents of the process tower have passed the conference;
(2) The foundation has been checked and accepted;
(3) Complete components with pre-assembly records;
(4) The construction equipment is complete, and engineers and field operators are in place.
(5) Before installation of the process tower, the supervisor must examine and approve the construction organization design or construction scheme and safety measures of the contractor. If a scheme does not meet the requirements, it must be ordered to redesign or modify it.